MLSE Scotiabank Venue Reimagingation Project

At a Glance

Ramcom successfully completed the Integration, Installation and commissioning of over 1630 LG LSCB Cabinets, creating over 19 DVLED Features using Nova H Series controllers mounted to Custom Atec Frames in this phase .

Project Scope

1

Initial support in project design & intergration

Attended and supported all design, structure/fabrication, and site meetings related to electrical, data, and fiber work, ensuring coordination in line with the scope of work (SOW).

2

Design, Integration and Deployment of Fiber & Copper feeds to each Asset/Feature

Procured, installed, and certified all fiber and copper feeds for digital assets, including fusion-spliced fiber backbones and Cat6 drops, ensuring full functionality and compliance.

3

Racks & Commissioning

Supplied and fully populated nine racks across the building, including dressing, labeling, and AS-built documentation, commissioned Nova H processors, and coordinated content cut-over and hand-off to the client for a complete turnkey solution.

4

Installation

Installed and precisely aligned LG rails and LSCB cabinets, routed cables for redundancy, aligned modules for seamless visuals, and completed finishing with LG trim edges where applicable.

5

Commissioning

Collaborated with LG to verify all Novastar H series controller programming and worked closely with MLSE staff to ensure all assets and features operated flawlessly at hand-off.

6

Close-Out

Met with WJHW, CAA ICON, MLSE, LG for final test and accept to ensure project was completed to spec.